April 17, 2023 11:33 AM
HAMILTON AVE / HWY 127 WATER LINE WORK (IN PROGRESS)
Full Project Description: This is an ODOT project that was originally expected to be completed in 2022, at the same time as the Mt. Healthy portion. GCWW did not confirm the water line replacement (NCH portion only) until after ODOT opened bids on the roadway work. The water line work has commenced, and is expected to be completed in August 2023. The roadway work is under the control of ODOT; however, it is expected to be completed in September/October 2023, approximately 1 month after the water line work is complete.
Project Schedule:
• GCWW Water line work – In progress. Expected completion August 2023.
• ODOT roadwork – Not started. Expected completion September/October.
Project Budget:
• Project Estimated Cost: $1,300,000
• ODOT Funding: $ 584,190
• OPWC Grant: $ 548,795
• SORTA Grant (not to exceed): $ 552,045