April 17, 2023 11:21 AM
BOBOLINK DRIVE WATER LINE WORK (IN PROGRESS)
Full Project Description: Originally bid in April 2022, including roadway work and GCWW water line work. All bids exceeded OPWC funding budget, and were rejected. The GCWW work was then separated from the roadway project. GCWW work is currently under way, and is anticipated to be completed spring 2023. Roadway plans are being revised to bring the cost in line with the OPWC budget.
Project Schedule:
• Water line replacement – Expected completion spring 2023.
• Re-bidding the roadway work – April 17, 2023 through May 10, 2023
• Roadway work – Late spring through November 2023.
Project Budget:
• Original Estimated Total Project Cost: $825,300
• OPWC Grant Amount: $412,650
• OPWC Loan Amount: $412,650