▼CURRENT PROJECTS
7 Alerts
April 17, 2023 11:41 AM
Full Project Description: Originally started in 2019, and anticipated to be completed in 2021, the renovation of Marshal Peter Dumele Park - including construction of a Splash Pad - was delayed by two years due to COVID-related closures & supply chain...
MARSHAL PETER DUMELE PARK RENOVATION (IN PROGRESS)Read On...
April 17, 2023 11:38 AM
Full Project Description: Water line replacement is not in scope for this project. Roadwork design is expected to be completed in October 2023, and bidding is expected to open in November 2023. No conflict is expected with the Hamilton Avenue water line...
GALBRAITH ROADWAY WORK (PENDING)Read On...
April 17, 2023 11:36 AM
Full Project Description: Similar project scope and schedule as Prospect Place. GCWW water replacement will impact this schedule. The roadway work should be complete by June, 2024.
Project Schedule:
• Roadwork engineering planning – In progress. Expected...
LARANN & DORDINE (PENDING)Read On...
April 17, 2023 11:35 AM
Project Description: Similar project scope and schedule as Prospect Place. GCWW water replacement will impact this schedule. The roadway work should be complete by June, 2024. Engineering planning is in progress, and is expected to be complete by July. ...
PROSPECT PLACE WATER LINE & ROADWAY WORK (PENDING)Read On...
April 17, 2023 11:33 AM
Full Project Description: This is an ODOT project that was originally expected to be completed in 2022, at the same time as the Mt. Healthy portion. GCWW did not confirm the water line replacement (NCH portion only) until after ODOT opened bids on the...
HAMILTON AVE / HWY 127 WATER LINE WORK (IN PROGRESS)Read On...
April 17, 2023 11:21 AM
Full Project Description: Originally bid in April 2022, including roadway work and GCWW water line work. All bids exceeded OPWC funding budget, and were rejected. The GCWW work was then separated from the roadway project. GCWW work is currently under way...
BOBOLINK DRIVE WATER LINE WORK (IN PROGRESS)Read On...
April 17, 2023 11:20 AM
Full Project Description: Originally bid in April 2022, including roadway work and GCWW water line work. All bids exceeded OPWC funding budget, and were rejected. The GCWW work was then separated from the roadway project. GCWW work is currently under way...
JOSEPH COURT & DODGEON COURT WATER LINE WORK (IN PROGRESS)Read On...